
Angat Water Utilization and Aqueduct Improvement Project (AWUAIP)
A. PROJECT:
A. PROJECT:
An estimated 97% of the water supply consumption of Metro Manila with an average of 4,000 million liters per day is coming from the Umiray, Angat and Ipo Dams. The water flows by gravity through a system of tunnels, basins, aqueducts and eventually channels down to the two treatment plants of La Mesa and Balara.
In January 2002, an inspection of the existing aqueducts revealed that about 13 leakages occur on some segments of the existing Bicti-Novaliches Aqueduct No. 5 (BNAQ-5) and 3 of these leaks were considered major leaks as it losses about 150 mld. The 3 major leaks were repaired but leaks continue to surface on the other weak points of the existing aqueduct. Hence, it was recommended to do no further repair but closely monitor the leaks and construct a new aqueduct to serve as by-pass during rehabilitation.
BNAQ-5 which was constructed in 1990 conveys 2000 MLD of raw water which is 50% of the total raw water from the Umiray, Angat and Ipo Dams. BNAQ-5 is in critical condition because of the leaks that if no immediate action can be done will endanger the almost 2000 MLD of water supply for Metro Manila.
Thus, for security of water supply to Metro Manila, it is vital that BNAQ-5 and the other existing aqueducts be assessed and rehabilitated as early as possible, and the urgent construction of a new aqueduct (BNAQ-6) to serve as by-pass during rehabilitation and to accommodate additional supply from Angat and Umiray River Basin.
In January 2002, an inspection of the existing aqueducts revealed that about 13 leakages occur on some segments of the existing Bicti-Novaliches Aqueduct No. 5 (BNAQ-5) and 3 of these leaks were considered major leaks as it losses about 150 mld. The 3 major leaks were repaired but leaks continue to surface on the other weak points of the existing aqueduct. Hence, it was recommended to do no further repair but closely monitor the leaks and construct a new aqueduct to serve as by-pass during rehabilitation.
BNAQ-5 which was constructed in 1990 conveys 2000 MLD of raw water which is 50% of the total raw water from the Umiray, Angat and Ipo Dams. BNAQ-5 is in critical condition because of the leaks that if no immediate action can be done will endanger the almost 2000 MLD of water supply for Metro Manila.
Thus, for security of water supply to Metro Manila, it is vital that BNAQ-5 and the other existing aqueducts be assessed and rehabilitated as early as possible, and the urgent construction of a new aqueduct (BNAQ-6) to serve as by-pass during rehabilitation and to accommodate additional supply from Angat and Umiray River Basin.
B. THE PROJECT:
The Project is the Angat Water Utilization and Aqueduct Improvement Project (AWUAIP), with the original objective of maintaining and optimizing the quantity of raw water delivered daily from Angat Dam via the Ipo Dam-Bicti-La Mesa Portal system to the water treatment plants. The new aqueduct (BNAQ-6) will be constructed in two phases. Phase 1 (5.5 km. length) will serve as by-pass while repairing existing BNAQ-5. Phase 2 entails the construction of the remaining section (9.90 km. length) and the construction of new water treatment plant.
C. OBJECTIVE:
The primary objectives of the Project are:
a) Ensure the safety and integrity of the raw water conveyance system from Ipo Dam to La Mesa Portals, thus maintaining the security of water source for Metro Manila; b) Maximize the Angat Dam raw water allocation to MWSS; and c) Expand the Concessionaires’ water treatment plant capacities to utilize recovered water allocated to MWSS.
a) Ensure the safety and integrity of the raw water conveyance system from Ipo Dam to La Mesa Portals, thus maintaining the security of water source for Metro Manila; b) Maximize the Angat Dam raw water allocation to MWSS; and c) Expand the Concessionaires’ water treatment plant capacities to utilize recovered water allocated to MWSS.
D. Importance of this Project:
To secure the existing water supply for Metro Manila coming from Angat Dam, and likewise to reduce the risk of possible shortage of the present water supply considering that the existing aqueduct no. 5 which was found leaking carries about 50% (2000mld) of the total water supply for Metro Manila.
E. PROJECT STATUS (as of 31 May 2008):
|
Description |
Estimated |
Source of Fund |
Status |
|
PhP 1,450 M |
GOP Funding |
|
b) Detailed Engineering Design - AQ-6 Phase 2 - Rehab of AQ-5 - Interconnection works
- two (2) new water treatment plants |
US$ 0.415M PhP5,751.10M US$ 84.00M |
ADB-TA Loan China Loan To be funded by the Concessionaires |
|
Download the full version
no videos







